69kV Subtransmission System Reliability

The new 69kV subtransmission line segments will provide additional connections from Riverside’s existing generation facilities to key substations to relieve the congestion (overloads) and provide sufficient power flow to meet existing electric system demand during normal and planned/unplanned outage conditions within Riverside’s electric system. In addition, the connections of the substations will allow for Riverside’s electric facilities to run effectively and efficiently. The project is designed to increase reliability and strengthen RPU’s subtransmission system.


Project Segments

Project construction will occur in multiple segments and will consist of the below:

Riverside’s Energy Resource Center (RERC) to Harvey Lynn Substation

Riverside’s Energy Resource Center (RERC) to Freeman Substation


Estimated Project Timelines

Mid 2019 – Early 2020
Underground conduit and structure installation.

Late 2019 – Early 2020
RPU Staging Yard construction

Early 2020 - Mid 2020
Drilled Pier Foundations for Steel Poles from RERC to Harvey Lynn Substation

Mid 2020 – Early 2021
Installation of Steel and/or Wood Poles and construction of overhead lines from RERC to Harvey Lynn Substation

Early 2021 – Mid 2021
Drilled Pier Foundations for Steel Poles from RERC to Freeman Substation

Mid 2021 – Mid 2022
Installation of Steel and/or Wood Poles and construction of overhead lines from RERC to Freeman Substation


Construction Gallery

Drilling machine utilized for the installation of drilled pier foundations

Cages installed in the ground for the drilled pier foundations

Concrete work performed for the installation of drilled pier foundations


Drilled pier foundation

Drilled pier foundation

Steel pole installed


FAQ

Answers to the questions you may have.


Historical Timeline


Item Date
Riverside Public Utilities (RPU) began holding public meetings throughout the environmental review process April 2006
RPU issued the Draft Environment Impact Report (EIR) for public review August 2011
Public Meeting Continued Notice December 18, 2012
City Council certified Final Environmental Impact Report February 5, 2013
Board of Public Utilities Authorization for Installation of three steel pole foundations, steel pole, and wood pole at corner of Doolittle Ave. and Van Buren Blvd. June 11, 2018
Board of Public Utilities Authorization for Electrical Conduit and Structures Installation

June 24, 2019
Board of Public Utilities Authorization for the 69kV Materials Yard

August 26, 2019
Board of Public Utilities Authorization for Drilled Pier Foundations & Potholing for RERC to Harvey Lynn line Board Report

November 25, 2019